This project scope definition checklist covers what to write down before work starts on a software project: what is in scope, what is out, what you are assuming, how work gets accepted and how changes are handled. Use it after you have the client's brief and before you commit to a price. Part 1 is a checklist for you; Part 2 is a short scope statement you fill in from it and send to the client.

How to use this template

  1. Go through Part 1 with the client's brief open, on a call with the client if you can. Tick an item only when the answer is written down.
  2. If an item doesn't apply but the client might assume it does, list it under out of scope. If nobody would assume it, skip it. For a small fix or a single feature, a few lines under each heading of Part 2 are enough.
  3. Turn every question you can't answer yet into a row in the assumptions table, with the answer you are pricing on and the person who will confirm it. If most requirements are still unclear, don't force a fixed scope: send the requirements clarification checklist first, or scope a short, paid discovery phase instead of the whole build.
  4. Fill in Part 2: replace every bracketed placeholder, and delete the example row and any option you don't use. The bracketed numbers are starting points to adjust, not standards.
  5. Send Part 2 to the client with your price or proposal, and get that version confirmed in writing before you start. It sits alongside your proposal or contract and doesn't replace either one: payment terms, code ownership and termination belong there. If your contract has its own acceptance or change terms, make sections 5 and 6 match them. Keep Part 1 for yourself.
  6. Once it is confirmed, don't edit the agreed version. Later changes go through the change process in section 6 of Part 2, and the change order template on this site covers the numbered document.

The template

Download (.md)

Part 1: Scope checklist

Project: [Project name]. Client: [Client name]. Brief dated: [Date].

Tick an item only when the answer is written down. The test for any line: someone who wasn't on your calls can read it and tell exactly what was agreed.

In scope

  • Goal: one or two sentences on what the project is for and who will use the result.
  • Deliverables: every item the client receives is named, such as [web app, API, admin panel, migration script, documentation].
  • Features: each one is written as something a person can do ("A customer can cancel a booking up to 24 hours before it starts"), not as a topic ("booking management").
  • Roles: each type of user is listed with what they can see and do, such as [admin, staff, customer].
  • Platforms: browsers, operating systems, devices and minimum versions are named.
  • Languages and regions: interface languages, currencies and time zones are named, and so is who supplies translations.
  • Integrations: each third-party service is named with its exact job and who holds the account.
  • Data: what gets migrated, from where, how many records, in what format, and who cleans it first. If it includes personal data, how you may access it is agreed.
  • Content and design: who supplies copy, images and designs, how many screens, and how many revision rounds are included.
  • Testing and quality: what you test and how, with a target number wherever one matters, such as [expected users, response time, backup frequency]. Security requirements are listed by name.
  • Hosting and accounts: which environments exist, who owns each account and who pays for it.
  • Milestones: what is delivered in what order, with target dates.
  • Handover: what the client gets at the end: repository access, credentials, deployment notes, training sessions.
  • Support after launch: how long you fix defects after go-live and what that covers.

Out of scope

Name the things a reasonable client might expect to be included. A catch-all line is worth having, but it won't stop a client assuming their feature was covered. A named exclusion is much harder to miss.

  • Anything the brief mentions or implies that you are not delivering is listed by name.
  • Features moved to a later phase are listed as later, with no date or price promised.
  • Platforms you won't build or test for: [native mobile apps, tablets, older browser versions].
  • Content work: [copywriting, translation, photography, logo and brand design].
  • Data work beyond the agreed migration: [cleaning, de-duplication, historic records].
  • Marketing work: [SEO, ad tracking, email campaigns, app store listings].
  • Legal and compliance work: [privacy notice, terms of sale, data protection review, security audits, certifications].
  • Third-party costs the client pays directly: [hosting, licenses, API usage, SMS, payment fees].
  • Systems you don't control: [the client's ERP, another vendor's API], including changes made to them after launch.
  • Work after the support period: [monitoring, updates, on-call].
  • Training and documentation beyond what is listed under handover.
  • A catch-all line is included: anything not listed as in scope is out of scope.

Assumptions

Write down only what would change days, price or dates if it turned out to be false. Each assumption needs someone who confirms it.

  • Open questions: every unanswered question that affects the price is listed with the answer you priced on.
  • Decision-maker: one named person on the client's side answers questions and approves work.
  • Response time: the client answers questions within [2] working days and reviews each delivery within the review period under acceptance.
  • Access: accounts, API keys, test environments and existing code are available by [date].
  • Third-party services: each one has usable documentation, a test environment and the functions you need. Mark the ones you have actually tried.
  • Content: final copy, images and data arrive by [date], in [format].
  • Existing systems: you have seen the code, database or server you are inheriting. If you haven't, say so.
  • Volume: about [number] users and [number] records at launch.
  • Technology: [stack and hosting] is agreed, and no client policy rules it out.
  • Your availability: your start date, [number] days a week on this project, and any planned time off.
  • Consequence: the document says what happens when an assumption proves wrong.

Acceptance

If two people could disagree about whether a criterion passed, rewrite it.

  • Every deliverable in scope has at least one pass-or-fail criterion.
  • Each criterion describes something a person can check: an action and the result they should see. "Works correctly" and "the client is happy" don't qualify.
  • Who accepts: a named person, and a named stand-in if they are away.
  • Where: the environment, browsers, devices and test data used for acceptance.
  • Review period: [5] working days from each delivery.
  • No response: what happens if the review period ends without an answer.
  • Defect or change: a defect fails a written criterion. A request for something different from what was written is a change.
  • Blocking or not: which issues hold up acceptance, which go on a fix list, and when that list gets cleared.
  • Reporting: where defects are reported and what a report must include.
  • Fix and re-test: how long you have to fix a defect and how long the client has to re-test.
  • Live use: whether putting the work into production counts as acceptance.
  • What acceptance triggers: the related payment, the next milestone, or both.

Change process

Agree this now, while nothing is in dispute.

  • Baseline: the version and date of the scope statement that changes are measured against.
  • Who can ask: the client's named contacts who can make a change request.
  • Channel: where change requests go, such as [email address or issue tracker]. A request made on a call or in chat gets written there before it counts.
  • Assessment: how quickly you reply with the effect on days, price and dates, or with the questions you need answered first.
  • Approval: no work starts on a change until the client has confirmed it in writing.
  • Change order: each approved change gets a numbered document showing price and dates before and after.
  • Pricing: changes are priced at your day rate of [amount and currency], or at a fixed price per change.
  • Small changes: either a limit on free ones, such as under [2] hours and up to [3] per milestone, or a clear statement that there are none. Free ones are still written down.
  • Removing work: taking something out follows the same steps, and the statement says how the price comes down.
  • Work in progress: what continues and what pauses while a change waits for a decision.

Before you start

  • The client's decision-maker has confirmed a specific version of the scope statement in writing.
  • Your price and dates were worked out from that same version.
  • Your proposal or contract refers to that version by number and date, and the statement says which applies if they disagree.
  • Every open question that could change the price is listed as an assumption.
  • You and the client both have a copy of the confirmed version, saved in [location].

Part 2: Scope statement

Send only this part to the client. Before you do, change the heading to "Scope statement: [Project name]", replace every bracketed placeholder and delete this line.

ItemDetails
Project[Project name]
Client[Client company]
Client's decision-maker[Name, email]
Delivered by[Your name or company, email]
Version and date[1.0], [Date]
Goes with[Proposal or contract reference]

In this document, "I" means [Your name or company] and "you" means [Client company]. This version replaces earlier versions and messages about scope. If it disagrees with the document named above, [which document] applies.

1. Goal

[Project name] will let [type of user] [do what], so that [business result].

2. In scope

I will deliver the items in this table. Each one is accepted when its check passes, following section 5. The list after the table gives the conditions for all of them.

#Deliverable or featureWhat it doesAccepted when
1[Name][What a named type of user can do][A check that either passes or fails]
2[Name][What it does][Check]
3[Name][What it does][Check]
Example row, delete before sending

Password reset. A customer can ask for a reset link by email and set a new password. Accepted when a test account receives the email, the link works once, and a used link shows an error.

  • Users and roles: [role and what it can do]; [role and what it can do].
  • Platforms: [browsers and minimum versions]; [devices or screen sizes].
  • Languages and regions: [interface languages, currencies, time zones]. Translations come from [you or me].
  • Integrations: [service]: [its exact job]. Account held by [you or me].
  • Data migration: [source, approximate record count, format], cleaned first by [you or me]; or none.
  • Content and design: [copy, images and designs] come from [you or me]. This covers [number] screens and [number] revision rounds.
  • Testing and quality: [what I test and how]; [agreed numbers, such as expected users or response times, or none].
  • Hosting: [provider], with [staging and production]. Accounts held by [you or me].
  • Milestones: I start on [date] and work [number] days a week on this project, with [planned time off, or none]. [Milestone 1: items 1 and 2, by date]; [Milestone 2: item 3, by date].
  • Handover: [repository access, credentials, deployment notes, training session length].
  • Support after launch: I fix defects you report within [30] days of go-live at no extra charge.

3. Out of scope

These are not part of this project. Anything not listed in section 2 is also out of scope. You can add any of it through section 6.

  • [Feature or deliverable from the brief that this project doesn't include]
  • [Later-phase items, with no date or price promised]
  • [Platforms not built or tested, such as native mobile apps or older browsers]
  • [Content and data work, such as copywriting, translation or cleaning data]
  • [Marketing work, such as SEO, ad tracking or app store listings]
  • [Legal and compliance work, such as privacy notices, terms of sale or security audits]
  • [Changes caused by systems I don't control, such as your ERP or another vendor's API]
  • Third-party costs, which you pay directly: [hosting, licenses, API usage, SMS, payment fees].
  • Work after the support period in section 2, such as [monitoring, updates, on-call].
  • Training and documentation beyond the handover in section 2.

4. Assumptions

My price and dates depend on these. If one turns out to be wrong, I will tell you and we will handle it through section 6.

AssumptionConfirmed byBy dateIf it turns out wrong
You answer questions within [2] working days and review each milestone within the period in section 5.[Name][Date]Dates move by the length of the delay.
I have access to [accounts, API keys, test environment].[Name][Date]Dates move by the length of the delay.
Final content arrives in [format].[Name][Date]Dates move by the length of the delay.
[Third-party service] has a test environment and supports [function].[Name][Date]I assess the alternative and send you the effect on days and price.
The project uses [stack and hosting], and no policy on your side rules it out.[Name][Date]I assess the alternative and send you the effect on days and price.
[Existing code, database or server]: [I have reviewed it, or I have not seen it and have assumed what I expect to find].[Name][Date][Effect on days or price]
Launch volume is about [number] users and [number] records.[Name][Date][Effect on days or price]
[Open question]: I have assumed [the answer I priced on].[Name][Date][Effect on days or price]

5. Acceptance

  • [Name and role] reviews and accepts the work on your side, or [stand-in's name] if they are away.
  • I deliver each milestone to [environment or address], with [test data], and tell you it is ready. You then have [5] working days to test it against the checks in section 2.
  • A defect is work that fails a check in section 2. Report defects in [issue tracker or email] with the steps you took, what you expected and what happened. I fix them within [3] working days, and you have [2] working days to re-test.
  • Issues that don't stop a check from passing, such as [small visual differences], go on a fix list and don't hold up acceptance. I clear that list by [date or milestone].
  • A request for something different from what is written here is a change, not a defect. It goes through section 6.
  • If the review period ends without a reply, or the work goes live, I will treat the milestone as accepted.
  • Acceptance of a milestone triggers [the related payment, the next milestone].

6. Changes

This version is the baseline. A change is anything that adds, removes or alters what is written here, however small.

  1. [Named contacts] send change requests to [email address or issue tracker]. If one comes up on a call or in chat, it counts once it is written there.
  2. Within [2] working days I reply with the effect on days, price and dates, or with the questions I need answered first.
  3. If you want to go ahead, I send a numbered change order showing price and dates before and after. Work starts once you confirm it in writing.
  4. Added work is priced at [day rate and currency] per day, unless the change order gives a fixed price. Removed work reduces the price by [the days removed at the same rate, less work already done].
  5. Work already in scope continues while a change waits for a decision. If the change affects it, I will tell you what pauses.
  6. [Choose one] Changes under [2] hours are free, up to [3] per milestone, and I still record them. Or: there are no free changes, and every change goes through these steps.

7. Confirmation

To confirm this version, reply to this message in writing or sign below. If something needs to change, tell me before you confirm. Work starts once you have confirmed it.

ForNameDateSignature or written confirmation
[Client company][Name][Date][Signature or reply reference]
[Your name or company][Name][Date][Signature or reply reference]

This template is a starting point, not legal advice. For contracts with significant value or risk, have a lawyer review the final text.