Software Developer Change Order Template

This software change order template records a change to a project that has already been agreed: what changes, why, and what that does to the scope, timeline and price. Use it when a client asks for something outside the agreement, or when an assumption behind it turns out to be wrong, and get it approved before you start the work. It points back to an existing agreement or accepted proposal, so if nothing was agreed in writing, write down the current scope first.

How to use this template

  1. Copy or download the template. Both give you Markdown, so work in an editor that renders its tables. Change the top heading to Change Order plus its number and the project name, and replace every bracketed placeholder. Delete rows and options that don't apply, and keep it short: a long change order reads like a renegotiation.
  2. Reread the original agreement before you fill anything in, and name the section the change touches. If the work is already covered, it doesn't need a change order. If you can't tell, ask the client a clarifying question before you price anything.
  3. Number change orders in one running sequence per project and never reuse a number. If a draft changes before approval, keep the number and raise the version, so only one approved version of each number exists.
  4. Estimate everything the change causes, not only the new code: rework in finished features, retesting, deployment and the effect on other milestones. Carry earlier approved change orders into the price table so the client sees the running total.
  5. In the assumptions, list only points that would move the timeline or price if they turned out to be wrong. If you decide to do a change for free and it affects scope or dates, still record it here using the no-charge option.
  6. Send it as a PDF to the person on the client's side who can approve the cost, and wait for approval before starting the work. Check your original agreement first: some contracts only accept signed changes, so an email reply may not be enough.

The template

Download (.md)

Change order details

FieldDetails
Change order number[CO-001]
Version[1]
Issue date[date]
Project[project name]
Client[client company or name, contact person, email]
Developer[your business or name, email]
Original agreement[document title and reference], dated [date]
Earlier approved change orders[none, or list their numbers]
Raised by[name] on [date], in [email, call, meeting or ticket reference]
Valid until[date]

Once approved in section 8, this change order changes the agreement named above (the Original Agreement) between the Client and the Developer, but only where this document says so.

1. Description of the change

[Describe the change in one to three plain sentences: what the software will do differently, and for whom.]

No.TypeWhat will be deliveredDone when
1[Add, change or remove][feature, screen, integration or document][what both sides can check to confirm it is finished]
2[Add, change or remove][feature, screen, integration or document][what both sides can check to confirm it is finished]

2. Reason for the change

  • The Client asked for something the Original Agreement does not include.
  • The Client asked to remove or reduce work.
  • The Client's requirements changed after the Original Agreement.
  • An assumption in the Original Agreement turned out to be wrong.
  • A third party changed something outside both sides' control, such as an API, a platform rule or a vendor's plan.
  • Other: [explain].

What happened: [State the facts briefly, with dates and who asked for what. Refer to the email, call or ticket if there is one.]

How this differs from the Original Agreement: [Section or clause] of the Original Agreement covers [what it includes, excludes or assumes]. This change [adds, alters or removes] [the work concerned].

3. Impact on scope

  • Added: [new features, screens, integrations or deliverables, or none]
  • Changed: [existing deliverables that will work differently, or none]
  • Removed: [deliverables taken out of scope, or none]
  • Rework: [finished work that must be redone or retested because of this change, and any data migration, or none]
  • Not included: [related work someone might reasonably assume is part of this change]

Apart from the items listed above, the deliverables and exclusions in the Original Agreement stay as written.

4. Impact on timeline

MilestonePlanned dateChangeNew date
[milestone][date][plus or minus number of working days][date]
Final delivery[date][plus or minus number of working days][date]

Work on this change starts within [number] working days of approval. The new dates assume approval by [date]; later approval may move them.

While this change is being done: [other work continues as planned, or name the work that pauses].

5. Impact on price

Cost of this change

ItemBasisAmount
[work item from section 1][number] days at [day rate] a day, or fixed[amount]
[rework and retesting from section 3][number] days at [day rate] a day, or fixed[amount]
[licence, service or other fixed cost][fixed or at cost][amount]
[credit for removed work, if any][number] days of work not yet done at [day rate] a day[minus amount]
Total for this change orderSum of the rows above[amount and currency]

Project price after this change

LineAmount
Price in the Original Agreement[amount]
Earlier approved change orders[amount, or 0]
Price before this change order[amount]
This change order[amount, minus if it is a net credit]
New project price[amount and currency]

Pricing basis: [keep one of the following and delete the others]

  • Fixed price: the total above is fixed for the work in sections 1 and 3, as long as the assumptions in section 6 hold.
  • Time and materials: the total above is an estimate. Work is billed at [rate] per [hour or day] and will not go over [amount] without the Client's written approval.
  • No charge: the Developer does this change at no charge. This does not commit the Developer to doing other changes at no charge.

Running costs: [New API fees, licences or hosting this change adds, who holds each account and who pays them, or none.]

Payment: [amount] is [invoiced on approval, invoiced on delivery of this change, invoiced with the next milestone, split between those points with an amount for each, or credited against the next invoice], on the payment terms of the Original Agreement. [Delete this line for a no-charge change.]

Tax: Amounts [include or exclude] [VAT or other applicable tax].

6. Assumptions

The timeline and price above depend on the points below. If one turns out to be wrong, the Developer will tell the Client before continuing the affected work, and both sides will agree what to do next. That may need a further change order.

  • The Client provides [access, credentials, content, test accounts or other inputs] by [date].
  • [Third-party service or API] offers [feature, plan or sandbox] and works as its documentation describes.
  • The Client gives feedback or sign-off within [number] working days of each request.
  • This change includes [number] revision rounds. Further revisions are quoted separately.
  • The work covers [platforms, browsers, environments or data volumes] only.
  • [Any other assumption this estimate depends on.]

7. Terms

  • The Developer starts this change only after it is approved in section 8.
  • If this change order and the Original Agreement differ on something covered here, this change order applies to that point. All other terms of the Original Agreement stay the same.
  • The price and dates here hold until the valid-until date above. After that, the Developer may revise them.
  • If the Client declines this change order, or does not reply by the valid-until date, work continues under the Original Agreement without this change.

8. Approval

Tick one option, sign below and return a copy to [email]. To change anything here, reply before signing and the Developer will send a new version under the same number.

[Optional, if the Original Agreement allows it: A written reply to the email carrying this change order, quoting its number and confirming approval, also counts as approval.]

  • Approved: go ahead with this change, including the new timeline and price.
  • Not approved: continue under the Original Agreement without this change.
DetailClientDeveloper
Company or name[client company or name][your business or name]
Signed by[full name][full name]
Role[role][role]
Signature
Date

This template is a starting point, not legal advice. For contracts with significant value or risk, have a lawyer review the final text.