# Software Project Pricing Worksheet

> **For your own use** This worksheet holds your day rate, your buffer and your reasoning. Send the client the price summary near the end, not these tables.

## Project details

| Field | Entry |
| --- | --- |
| Project | [Project name] |
| Client | [Client name] |
| Prepared by | [Your name] |
| Date and version | [YYYY-MM-DD], version [1] |
| Based on | [Brief, email thread or scope document, with its date] |
| Currency | [USD, EUR, TRY or other] |

## Inputs

| Input | Value | How to set it |
| --- | --- | --- |
| Day rate | [amount] per day | What one billable day costs the client. It has to cover your unbilled time, costs and tax; this worksheet can't tell you what the market pays. Fix it before you estimate, so you can't quietly lower it later to reach a total you had in mind. |
| Hours in a working day | [8] | What one day means in your estimates. Use the same figure in every row. |
| Risk buffer | [15]% | Extra days for risks you can't list as tasks yet. Known work goes in a task row instead. |

| Buffer | When it fits |
| --- | --- |
| 8 to 10% | Repeat work for a client you know, clear requirements, no new tools. |
| 15% | Requirements mostly clear, one or two unknowns, a client you haven't worked with before. |
| 25% | Third-party integrations you haven't used, gaps in the brief, several people signing off. |

If you'd want more than 25%, the scope probably isn't ready to price. Get answers to the open questions first, or quote a paid discovery phase.

## Development tasks

**Weighted days = (best + 4 × likely + worst) / 6.** This is the standard three-point (PERT) weighting. It stays close to your likely figure, and a long worst case pulls it up. It is only as good as the three numbers you give it.

- **Best:** the task goes as planned and nothing surprises you.
- **Likely:** the number you'd give if you could give only one.
- **Worst:** a realistic bad case, such as an awkward API or rework after a review. Not a disaster.

| Phase | Task | Best | Likely | Worst | Weighted |
| --- | --- | --- | --- | --- | --- |
| Foundation | [Repo, environments, CI] | [days] | [days] | [days] | [weighted] |
| Foundation | [Data model and migrations] | [days] | [days] | [days] | [weighted] |
| Backend | [Task] | [days] | [days] | [days] | [weighted] |
| Backend | [Task] | [days] | [days] | [days] | [weighted] |
| Frontend | [Task] | [days] | [days] | [days] | [weighted] |
| Frontend | [Task] | [days] | [days] | [days] | [weighted] |
| Integration | [Third-party service or API] | [days] | [days] | [days] | [weighted] |
| Testing | [Automated tests for the critical paths] | [days] | [days] | [days] | [weighted] |
| Testing | [Fixes after client testing] | [days] | [days] | [days] | [weighted] |
| Release | [Production deployment and monitoring] | [days] | [days] | [days] | [weighted] |
| **Development subtotal** |  | [sum] | [sum] | [sum] | [sum] |

**Notes:** [Why any worst figure is more than three times its likely figure]

## Non-development time

This is billable work the project needs that isn't code, and it's easy to leave out of an estimate. Estimate it the same way. Put 0 where a row doesn't apply and note why.

| Activity | Best | Likely | Worst | Weighted |
| --- | --- | --- | --- | --- |
| Kickoff and requirements clarification | [days] | [days] | [days] | [weighted] |
| Calls, status updates and client email | [days] | [days] | [days] | [weighted] |
| Getting access: accounts, credentials, test data | [days] | [days] | [days] | [weighted] |
| Supporting client acceptance testing | [days] | [days] | [days] | [weighted] |
| Change requests and project admin | [days] | [days] | [days] | [weighted] |
| Documentation and handover | [days] | [days] | [days] | [weighted] |
| Support window after launch | [days] | [days] | [days] | [weighted] |
| [Other: training, travel] | [days] | [days] | [days] | [weighted] |
| **Non-development subtotal** | [sum] | [sum] | [sum] | [sum] |

**Notes:** [Why any row is 0]

**Leave out:** sales calls, writing the proposal, holidays, taxes and your own software subscriptions. Your day rate has to cover those. Licences and paid services bought for this project aren't days either, so list them separately in the proposal.

## Totals and price range

| Line | Calculation | Result |
| --- | --- | --- |
| All tasks, weighted | Development subtotal + non-development subtotal | [days] |
| Risk buffer | All tasks × buffer % | [days] |
| Days including buffer | All tasks + risk buffer | [days] |
| **Low end of range** | All tasks × day rate | [currency] [amount] |
| **High end of range** | Days including buffer × day rate | [currency] [amount] |
| Midpoint | (Low end + high end) / 2 | [currency] [amount] |

Quote inside this range. Below the low end you are charging less than the estimated work, with nothing for risk. A fixed price leaves overruns with you, so start from the high end. Use the midpoint when someone needs one planning figure, not as a commitment. Keep the decimals while you calculate and round only the final prices, so rounding doesn't add up across rows.

### Stress test (not a quote)

| Case | Calculation | Result |
| --- | --- | --- |
| Every task at best | (Development best + non-development best) × day rate | [currency] [amount] |
| Every task at worst | (Development worst + non-development worst) × day rate | [currency] [amount] |

Tasks rarely all go well or all go badly at once, so neither figure is a fair price. Use the worst case to ask one thing: if most of this went wrong on a fixed price, could you absorb it? If not, split the work into phases, narrow the scope, or quote a range.

## Checks before you send a price

The 5-day and three-times limits are rules of thumb. Change them if your own projects suggest otherwise.

- [ ] Every requirement in the brief maps to a task row or is listed as excluded.
- [ ] Any task with a likely estimate over 5 days is split into smaller tasks.
- [ ] Any task whose worst is more than three times its likely has a written reason, and that reason is an assumption or a question for the client.
- [ ] Open questions are answered, or written down as assumptions in the price summary.
- [ ] The buffer covers unknowns only. Known work has its own row.
- [ ] Non-development rows are filled in, or set to 0 with a reason.
- [ ] Days including buffer fit your calendar before [delivery date].

## Price summary for the client

Pick one, fill it in from the totals above, and paste it into your proposal or email. Neither states your buffer, day rate or day count. Work out the weeks from days including buffer and your calendar. Share the day count only if you're happy for the client to see your rate: the high end divided by days including buffer gives it.

> Estimated range: Based on [brief or scope document] dated [date], I estimate this project at [currency] [low end] to [currency] [high end], with delivery about [number] weeks after kickoff. That covers [what's being delivered], plus kickoff, calls, support during your testing, and handover. It doesn't cover [exclusions]. It assumes [assumption 1] and [assumption 2]. If an assumption turns out to be wrong, or you'd like something outside this scope, I'll send a written change order with the added price and time, and start that work once you've approved it. This estimate is valid until [date].

> Fixed price: The fixed price for this project is [currency] [amount], based on [brief or scope document] dated [date], with delivery about [number] weeks after kickoff. It covers [what's being delivered], plus kickoff, calls, support during your testing, and handover. It doesn't cover [exclusions]. It assumes [assumption 1] and [assumption 2]. Work outside this scope, or work caused by a wrong assumption, is priced separately in a written change order and starts once you've approved it. Payment: [payment schedule and milestones]. This price is valid until [date].

## Filled sample: booking web app

> **Illustrative figures** An invented project. The numbers show how the worksheet works. They aren't benchmarks for what this work should cost or how long it should take. Delete this section when you use the worksheet.

| Input | Sample value |
| --- | --- |
| Project | Booking web app with online payments |
| Day rate | USD 500 per day |
| Hours in a working day | 8 |
| Risk buffer | 15% |

### Sample development tasks

| Phase | Task | Best | Likely | Worst | Weighted |
| --- | --- | --- | --- | --- | --- |
| Foundation | Repo, environments and CI pipeline | 1 | 2 | 3 | 2 |
| Foundation | Data model and migrations | 1 | 2 | 3 | 2 |
| Backend | Sign-in and user roles | 1 | 2 | 3 | 2 |
| Backend | Booking rules and availability | 3 | 5 | 7 | 5 |
| Frontend | Customer booking flow | 3 | 4 | 5 | 4 |
| Frontend | Admin screens | 2 | 3 | 4 | 3 |
| Integration | Payment provider, including refunds | 2 | 3 | 10 | 4 |
| Integration | Transactional email | 1 | 2 | 3 | 2 |
| Testing | Automated tests for booking and payment paths | 2 | 3 | 4 | 3 |
| Testing | Fixes after client testing | 1 | 3 | 5 | 3 |
| Release | Production deployment and monitoring | 1 | 2 | 3 | 2 |
| **Development subtotal** |  | **18** | **31** | **50** | **32** |

### Sample non-development time

| Activity | Best | Likely | Worst | Weighted |
| --- | --- | --- | --- | --- |
| Kickoff and requirements clarification | 1 | 2 | 3 | 2 |
| Calls, status updates and client email | 1 | 2 | 3 | 2 |
| Getting access: accounts, credentials, test data | 0 | 1 | 2 | 1 |
| Supporting client acceptance testing | 0 | 1 | 2 | 1 |
| Change requests and project admin | 0 | 1 | 2 | 1 |
| Documentation and handover | 1 | 1 | 1 | 1 |
| Support window after launch (quoted separately) | 0 | 0 | 0 | 0 |
| **Non-development subtotal** | **3** | **8** | **13** | **8** |

### Sample totals and price range

| Line | Calculation | Result |
| --- | --- | --- |
| All tasks, weighted | 32 + 8 | 40 days |
| Risk buffer | 40 × 15% | 6 days |
| Days including buffer | 40 + 6 | 46 days |
| **Low end of range** | 40 × USD 500 | **USD 20,000** |
| **High end of range** | 46 × USD 500 | **USD 23,000** |
| Midpoint | (20,000 + 23,000) / 2 | USD 21,500 |
| Stress test: every task at best | (18 + 3) × USD 500 | USD 10,500 |
| Stress test: every task at worst | (50 + 13) × USD 500 | USD 31,500 |

The payment row has the widest spread because refunds haven't been confirmed in the provider's test environment, so that goes in the summary as an assumption. Support after launch is 0 because this sample quotes it separately. The worst case is USD 8,500 above the high end: on a fixed price of USD 23,000, that is the exposure you would be accepting. 46 days is a little over 9 weeks at five days a week; the sample summary says 12 to leave room for client reviews and other work.

> Sample summary for the client (illustrative): Based on your brief, I estimate the booking web app at USD 20,000 to USD 23,000, with delivery about 12 weeks after kickoff. That covers customer booking, admin screens, card payments with refunds and transactional email, plus kickoff, calls, support during your testing, and handover. It doesn't cover support after launch, native mobile apps or moving data from your current system. It assumes the payment provider's test environment supports refunds and that one person on your side signs off each stage. If an assumption turns out to be wrong, or you'd like something outside this scope, I'll send a written change order with the added price and time, and start that work once you've approved it. This estimate is valid for 30 days.